Integrated Services project – Update Jan 25 2010

Integrated Services project – Update Jan 25 2010

• Excessive noise levels to be stopped at 10am everyday.
• Sanding of concrete floors – on going until next week.
• Demolition of internal façade – To start next week or early February – this step will be noisier than 1st days when external façade was demolished.
• Relocation of data and electrical wires for McLennan main floor – desktops located in main area to be affected. There are 4 main electrical boxes that control area where desktops are installed; Kingston Byers and McGill electricians are performing tests (BEFORE THE STUDENTS ARRIVE) to see which areas get affected.
For box 1 section will be closed for 2 days starting tomorrow. Students can still use tables although no electricity will be available on them. If other areas are affected other than the ones mentioned below , please notify Facilities , call Rosaire Gagnon 514 984 -9464 or Facilities , local 4555.
Areas affected:
M1-43A West wall - 3 desktops- Newspaper area – (behind Carole Urbain’s office.)
Complete area – West side of the McLennan e-zone (Sherbrooke St)

M1-76 North wall desktops which are the 3 desktops (next to the Fire Hose ) all along Sherbrooke St)
SIGNS HAVE also BEEN PUT UP.

• For the other sections located on same floor – electrician will do test on the following days and based on results they will coordinate with Libraries.


Francisco Oliva
Planning & Resources